James Bryan Bacon

ATTORNEY & COUNSELLOR AT LAW

P.O Box 575

New Paltz, New York 12561

--------

Telephone (845) 255-2026

Facsimile (845) 255-8925

 

                                                                                                            September 25, 2006

 

Mr. Herb Schech, Chairman

Town of Patterson Planning Board

P.O. Box 470

1142 Route 311

Patterson, New York 12563

 

Re: Patterson Crossing

 

Dear Mr. Chairman and Members of the Board:

 

            The Croton Watershed Clean Water Coalition, Inc. (CWCWC) and the Putnam County Coalition to Preserve Open Space (PCCPOS), submit the following comments on the above project’s Draft Environmental Impact Statement (DEIS) as proposed by Patterson Crossing Realty, LLC (Applicant) to supplement the comments made at the project’s public hearing.

 

We find that the project is dramatically out of scale with the surrounding area and that the DEIS is deficient in failing to include sufficient information of the project's traffic, stormwater, hydrogeological, rare and endangered species impacts and fails to adequately assess the project's conformance with the Town Codes of Patterson and Kent.  Therefore, a Supplemental Environmental Impact Statement is necessary and required under SEQRA.

 

            SEQRA PROCESS - STATE OF INFORMATION IN EIS

 

            CWCWC and PCCPOS have objected for years to the boilerplate information and responses typically given in Environmental Impact Statements prepared by the Applicant’s consultant.

 

            The New York State Supreme Court Appellate Division’s landmark ruling on August 8, 2006 in Matter of Riverkeeper, Inc. v Planning Bd. of Town of Southeast  2006 N.Y. Slip Op. 06160 proves that a lead agency’s acceptance of boilerplate information and blanket reliance on post-SEQRA agency review by the New York City Department of Environmental Protection (DEP), New York State Department of Environmental Conservation (DEC), the Army Corps of Engineers (ACOE) violates SEQRA.

 

            The Appellate Court reversed the Westchester County Supreme Court’s determination which had upheld the Town of Southeast’s decision that no Supplemental EIS (SEIS) was necessary for the 104-unit Meadows at Deans Corners housing development.

 

            In light of this decision, for Patterson Crossing, Tim Miller Associates should describe in detail in each category of potential impacts, i.e., including traffic, stormwater, endangered species and hydrogeology, how the developer will avoid the Meadows scenario, describing the elements of the Court’s determination that are particular to the Croton Watershed, such as phosphorus impacts and preserving the integrity of the watershed.

 

            Tim Miller Associates former responses concerning these issues such as provided in EISs for projects such as Hillcrest Commons in the Town of Carmel no longer suffice. The lead agency cannot escape its review obligations by relying on statements by Tim Miller Associates such as:

 

“The compliance with agency standards assures that no adverse impact will occur.” (Hillcrest Commons FEIS. at 11-4).

           

For years CWCWC has argued that Miller’s interpretation of the law was wrong citing such cases as Golten Marine Co. v. State Dept. of Envtl. Conservation, 193 A.D.2d 742, 743 (2nd Dept. 1993) which states:

 

“The fact that other agencies may have had an independent obligation to analyze the potential impacts of the facility had no bearing on [the lead agency’s] own obligation to analyze the listed areas of environmental concern.”

 

            More is required in an EIS than simply repeating a comment made on the DEIS and responding “so noted,” or providing a non-responsive answer.

 

            Indeed: Similarly,  in comparing SEQRA to federal law the Court stated:

“[T]he requirement of a detailed statement helps insure the integrity of the process of decision by precluding stubborn problems or serious criticism from being swept under the rug. A conclusory statement ‘unsupported by empirical or experimental data, scientific authorities, or explanatory information of any kind’ not only fails to crystallize issues * * * but ‘affords no basis for a comparison of the problems involved with the proposed project and the difficulties involved in the alternatives.’ Monroe County Conservation Council v. Volpe, 472 F.2d 693, 697 (2d Cir. 1972). Moreover, where comments from responsible experts or sister agencies disclose new or conflicting data or opinions that cause concern that the agency may not have fully evaluated the project and its alternatives, these comments may not simply be ignored. There must be good faith, reasoned analysis in response.” (Bliek v. Town of Webster, 104 Misc.2d 852, 862, 863 (Sup. Ct. Monroe Co. 1980)).

           

            Like the Meadows case, Patterson Crossing presents a host of complex and significant impacts many of which appear to be insurmountable.

 

            Based on the review of the DEIS by responsible experts such as John Canning, P.E., David Clouser, P.E., hydrogeologist John Conrad and Marian Rose, Ph.D., an SEIS is required to cure the omissions and inaccuracy of data supplied in the DEIS.

 

            SEQRA’s MANDATE

 

            SEQRA’s enabling legislation requires much from a lead agency stating:

 

“Agencies shall use all practicable means to realize the policies and goals set forth in this article, and shall act and choose alternatives which, consistent with social, economic and other essential considerations, to the maximum extent practicable, minimize or avoid adverse environmental effects, including effects revealed in the environmental impact statement process.” (E.C.L.  §8-0109(1)).

 

            STORMWATER AND PHOSPHORUS IMPACTS

 

In January 1997, the EPA in partnership with the State of New York, the City of New York, Putnam County, Riverkeeper and other parties forged the New York City Watershed (“MOA”) to protect and rehabilitate reservoirs within the Croton.

 

The 1997 Memorandum of Agreement (MOA) initiated NYC Watershed protection and partnership programs and detailed other watershed protection provisions including establishing more stringent Watershed Rules and Regulations (WR&R).

 

The Town of Patterson joined as a party to the MOA agreeing “to be bound by the terms and conditions thereto” and as a signatory agreed that:

 

“[A]n adequate supply of clean and healthful drinking water is vital to the health and social and economic well being of the People of the State of New York; and…

 

…it is the intention of the Parties to assure the continued adequate supply of exceptional quality drinking water for the eight million residents of the City of New York and the one million New York State residents outside the City who depend upon the New York City drinking water supply system; and… 

 

…the New York City water supply is an extremely valuable natural resource that must be protected in a comprehensive manner; and…

 

…it is the intention of the Parties to enter into a new era of partnership to cooperate in the development and implementation of a Watershed protection program that maintains and enhances the quality of the New York City drinking water supply system; and…

 

…the Parties now enter into legally enforceable commitments, as set forth in this Agreement, on issues related to the Watershed protection program, including the Watershed rules and regulations… and…

 

…the Parties have agreed to act in good faith and to take all necessary and appropriate actions, in cooperation with one another, to effect the purposes of this Agreement.”

           

            To implement these goals, Patterson agreed among others things to:

 

A)                Participate in the development of a Comprehensive Croton System Water Quality Protection Plan (“Croton Plan”) pursuant to §18-82 of the WR&R jointly with DEP and Putnam County,  and;

 

B)                Comply with the CWA by following EPA’s TMDL developed by DEP and DEC requiring reductions in the phosphorus pollutant loadings of downstream reservoirs.

 

            In implementing the TMDL program the WR&R stated that:

 

“USEPA will provide technical support in the development of TMDLs and review and approve submitted TMDLs. The water quality management goal of the TMDL program is to assure that the total phosphorus loading from point and non-point sources into a reservoir does not cause a contravention of the water quality standard for phosphorus.” (Id. and MOA at 162).

 

            In  July 2000, the Attorney General urged EPA to adopt TMDL standards that would reverse phosphorus contamination and issued a report targeting the pollutant for immediate reduction “Reducing Harmful Phosphorus Pollution in the New York City Reservoirs through the Clean Water Acts Total Maximum Daily Load Requirements: A Case-Study of the New Croton Reservoir and Recommendation to EPA” stating:

 

“One of the most important functions of my office is to protect and improve drinking water quality for the millions of New Yorkers who consume water from the New York City watershed,” said Spitzer. “It is imperative that phosphorus be effectively controlled to prevent a biological chain reaction from contaminating our drinking water.” (Emphasis added).

 

            Similarly, the WR&R requires:

 

“When any activity… is proposed to be undertaken in a phosphorus restricted basin, the stormwater pollution prevention plan shall include an analysis of phosphorus runoff, before and after the land disturbance activity.”  (WR&R §18-39(c)(1)).

 

            DEC’s regulations further provide:

 

“[N]o SPDES or other permit shall be issued authorizing any such discharge:

 

 (e) When the conditions of the permit do not provide for compliance with the applicable requirements of the CWA, or regulations promulgated under the CWA; and…

 

…The provisions of each issued SPDES permit shall ensure compliance with…  more stringent limitations, including those:

 

(ii) necessary to implement a total maximum daily load/wasteload allocation/load allocation established pursuant to Section 303(d) of the Act and 40 CFR Part 130.7.”  (6 NYCRR §§750-1.3(e), 1.11(a)(5)(ii)).

 

In calculating phosphorus loadings, in a 2000 report, EPA recommended that the most conservative measures available be used stating:

“Consistent with New York State's General Permit, NYCDEP's guidance allows the applicant to cho[o]se from a number of different methods in making calculations. Model selection depends upon a number of variables including the size of the land disturbance and the amount of input data. However, it is important that estimations include as much site-specific data as possible and that the most conservative measures are utilized to reduce stormwater loadings.

 

Regardless of which model is used to develop SPPPs, the result must be BMPs that are designed, built and maintained, consistent with Section 18-39 of the WR&R with an overall goal of no net increase in loadings over pre-existing construction conditions. EPA recommends that NYCDEP ensure that SPPPs include as much site-specific data as possible and that the most conservative measures are utilized to reduce stormwater loadings." (“Assessing New York City’s Watershed Protection Program” (May 2000), pg. 190, 192).

 

1.      Pollutant Loading - Pre-Development Levels

 

DEP studies conducted on the Croton watershed in Putnam County showing baseline phosphorus export levels of .0446 pounds per acre per year for forested areas.

 

However, rather than using .0446, the Applicant used .10 lbs. per acre per year relying upon a 1992 DEC publication. The DEC 1992 predevelopment phosphorus export levels are not specific to the Croton Watershed and that publication is no longer applicable. Indeed, according to Watershed Inspector General James Tierney, it is “outdated and defunct.”

 

Consequently, the Applicant’s calculations are incorrect by a factor of 2.24. 

 

Therefore, for the predevelopment existing conditions, less than half as much phosphorus is exported from the site as compared with the Applicant's estimates.

 

Tim Miller Associates has previously argued that because DEP has not formally adopted the figures in its stormwater review procedures, the .0446 figure is not relevant to the lead agency’s review obligations. This reasoning is wrong.

 

The .0446 figure was formally adopted by DEP in 2002 as accurate and was relied upon by DEP, EPA and DEC in developing the baseline data for the TMDL calculations for the Croton Watershed’s reservoirs.

 

If the entire TMDL program developed by DEP, EPA and DEC is founded on the .0446 figure, then it is inappropriate for the lead agency to use any other figure.

 

Furthermore, the EPA recommended that the most conservative approach available be used in modeling phosphorus impacts. Was EPA wrong? Is the .0446 figure more conservative than the .10 figure from 1992, which James Tierney stated was outdated and defunct?

 

The Applicant should answer these questions directly, in consultation with Mr. Tierney, especially in light of the Appellate Court’s ruling in Matter of Riverkeeper.

 

As SEQRA further requires that “to the maximum extent practicable” the lead agency “minimize or avoid adverse environmental effects” of a project, the lead agency must demonstrate that a project will not only maintain phosphorus pollutant loadings at pre-development levels, but actually reduce those levels pursuant to the TMDL program. (See “Non-Point Source Implementation of the Phase II TMDLs” (April 2001, Table 4.1 pg. 15)).

           

            TRAFFIC

 

Based on the project's size of 434,050 sq. ft., the project will generate up to 23,000 vehicle trips on a Saturday on its access drive. (Comments of Traffic Engineer John Canning citing ITE standards). On average that is 3.5 to 5.3 times more the daily traffic on Rt. 311. (Town's Comprehensive Plan at pg. 15).

 

An average weekday would bring 17,600 vehicle trips (8,800 cars) on average, every day during the week - more than double the traffic counts on Rt. 311 identified in the Comprehensive Plan.

 

To place the magnitude of the impact in context, it would be as if the number of families in both Towns increased by 36% and all drove to the project site every day, on top of the existing traffic.

 

Saturday traffic would be a worse nightmare  - It would be as if every family in both Towns increased by 79% and all drove back and forth to the project site in addition to all the other cars and trucks on Rt. 311 on a Saturday.

 

 This cannot occur. Traffic would be brought to a standstill and the rural character of the community would be destroyed forever. The net effect would be as if all of the families in two additional Towns the size of Patterson and Kent decided to drive their car every day into Kent and Patterson severely disrupting our quality of life and the existing transportation network.

 

What multiple of daily traffic is deemed acceptable? Is there a multiple that would be unacceptable? Is doubling the existing traffic too much? What about increasing traffic by five-fold as here? Is that enough? Is ten times more traffic enough? Can any further development occur following Patterson Crossing?

 

            SEWAGE

 

            The Town Code prohibits using a residential district for purely commercial purpose. is this use

Consider sewage - requires 8.7 acre sewage field, no where in permitted, especially in a residential zone.

 

The Applicant plans to cut, blast and fill a total of 566,500 c.yds. of soil and rock, enough to fill a football field with 318 feet of soil and rock. Where are the Applicant's details as to the site's hydrology?  Why don't the soil boring maps show testing in the 8.7 acre septic field? What empirical evidence is cited to prove the seasonal depth of the water table?

 

RARE AND ENDANGERED SPECIES

 

Tim Miller Associates has not demonstrated the expertise to identify endangered and rare species. Indeed, on the Hillcrest Commons site in Carmel, Hudsonia positively identified 24 locations of the endangered species Galium Concinnum or Shining Bedstraw. These locations were not identified by Tim Miller Associates.

 

This issue cannot be ignored. In Integrated Waste Systems Inc., (Supplemental Ruling July 24, 1995 DEC Project No. 9-0438-00004/00003-9), DEC ruled that plants listed as threatened deserve adequate review and protection measures by a lead agency. In referring to the 6 N.Y.C.R.R. §193.3(b) threatened plant species hypericum prolificum, DEC ruled:

 

"The plant's presence does, however, warrant mitigation measures to minimize any potential adverse impacts on the threatened plant species and its critical habitat, even if those adverse impacts are caused by the owner of the land on which the plants occur." (http://www.dec.state.ny.us/website/ohms/decis/integrsr.htm).

 

The lead agency should require the applicant to conduct appropriate studies as directed by Hudsonia's Biodiversity Assessment Manual and require that qualified personnel conduct the searches, such as a Certified Biologist.

 

NOISE

 

CWCWC's preliminary findings are that the neighbors will suffer from undue noise impacts from the project which will not be adequately mitigated by the proposed mitigation measures. The details of these findings are underway and will be submitted at their earliest availability.           

 

ECONOMICS

 

Concerning the DEIS's claim of 16 million in sales tax, the DEIS admits that "it is not known what the actual net increase may be as the spending patterns of persons in the trade area of the proposed shopping center are undocumented." (DEIS 3-5).

 

Despite being unknown, the DEIS  states up to 16 million dollars in sales tax is "projected."  How can it be projected when it is entirely unknown? The answer is that it cannot.  There is no basis for the DEIS's reckless claim which should be stricken from the record. The DEIS admits it has no basis for such a claim.

 

Also the DEIS examined a trade area radius of only 3 miles,  conveniently avoiding analysis of Brewster Highlands which is 3.5 miles away.  How much of the income derived from the project will simply be displaced dollars? What will it do to existing businesses? How can the DEIS possibly indicate that if the project creates 516 jobs, no additional people will wind up living in Kent or Patterson and not a single additional schoolchild will result. If that is not ludicrous, provide the data.

 

Where are the people going to come from seeking these $15-20,000 dollar jobs? The DEIS does not say. How is that going to impact traffic patterns? Again the DEIS is silent. They are not likely to come from Kent or Patterson where unemployment is very low and the median household income is between $66 and 72,000 dollars.

 

ARCHAEOLOGICAL IMPACTS

 

New York State Office of Parks, Recreation and Historic Preservation recently adopted new standards.  The Applicant must examine whether additional studies are required in light of the new standards.

 

ZONING

 

            The project will require a number of use and area variances by Patterson ZBA as follows:

 

·         The Zoning Code states for a Regional Retail Center that "Access shall be only from a State or County Road." The access point into the Town of Patterson is from an adjacent parcel in the Town of Kent. Therefore, a use variance is required. (§154-11(A)).

 

·         The access drive is 3,500 feet long - approximately 2,900 feet is in the Town of Patterson.  Whether defined as a street or driveway it needs an area variance. The Town Code limits cul-de-sacs to 1,500 feet (§138-32(F) and limits driveway lengths to 2000 feet. (§138-31(A)).

 

·         A use variance is also required because the Town Code prohibits using 8.7 acres of R-4 zoned property as an accessory use to service a commercial project. A commercial sewage field is not a residential use. This use is not allowable under the Code's Permitted Principal and Accessory Uses for the R-4 District. (§154-26 and 27).

 

As this is a coordinated review, the lead agency must consider and discuss the standards for granting use variances. Where is the economic hardship in dollars and cents? What are the real property value impacts to adjoining and nearby neighbors. Studies indicate that the creation of the currently proposed project will have devastating impacts to the Town's infrastructure and community character. (See Attached Riverkeeper Report).

 

How does the project conform with the Town's Special Use Permit Standards and Guidelines (§154-93(A)(2)), which state:

 

The ZBA determination "shall be made in accordance with the… requirements of this chapter including the need to lessen congestion in the streets… to promote health and general welfare… to prevent overcrowding of land… to facilitate adequate provisions of transportation… [and] sewerage."

 

            Does increasing the traffic by five-fold "lessen congestion in the streets" and promote the public welfare?

 

PATTERSON COMPREHENSIVE PLAN

 

The Town of Patterson Comprehensive Plan and Zoning Code do not envision a project anywhere near the magnitude of this project.

 

            The Zoning Code identifies a Regional Retail Center starting at 75,000 sq. ft. This project at 434,050 sq. ft. is 5.7 times the Zoning Code's figure, far beyond the size contemplated by the Code.

 

            SEQRA specifically allows a lead agency to require examination of “scale or magnitude” alternatives.  (6 N.Y.C.R.R. §617.9(b)(5)(v)(c)).

 

            Courts have held that lead agencies have acted within their SEQRA authority to require consideration of reduced scale alternatives and accept smaller versions of applicants’ preferred proposals discussed in the EIS. (See Sprint Spectrum L.P. v. Willroth, 996 F.Supp. 253 (W.D.N.Y. 1998) where single cellular tower chosen rather than alternative of three towers; and see Coalition for Responsible Planning v. Koch, 148 A.D.2d 230, (1st Dept. 1989) leave to appeal denied, 75 N.Y.2d 704 (1990) where the SEQRA review resulted in a “detailed comparison of the environmental impacts of all four alternatives” which included 500 fewer housing units than the developer’s preferred alternative of 1001 units.

 

            In fact, Courts have struck down a DEIS that fails to consider reasonable smaller-sized projects.  (See for example Grape Hollow Residents’ Ass’n v. Beekman Planning Board, No. 1986/284 (Sup. Ct. Dutchess Co. Oct. 16, 1986) where the subdivision’s opponents preferred a smaller number of units).

 

Similarly, in Brookville Taxpayers Ass’n, Inc. v. Town of Oyster Bay, N.Y.L.J., May 8, 1985 at 15, col. 3 (Sup. Ct. Nassau Co.) the Court struck down the Town’s rezoning holding that a reduced density alternative should not have been ignored  as the proponent had not shown that the reduced density alternative was “economically unfeasible.” (See also In re Bonded Concrete, Inc. (DEC Commissioner Decision, Apr. 9, 1984) where DEC denied an application for a sand and gravel mine because “no attempt has been made to evaluate the feasibility of alternative size or configurations of the areas on the Site to be mined.”)

 

The Board as lead agency has the obligation to set forth a reasonable range of alternatives and choose the alternative that minimizes the project's impacts to the maximum extent practicable.  Reasonable alternatives should be presented that comply in all respects with the zoning of both Kent and Patterson.

 

In sum, the DEIS is deficient and an SEIS is required.  The project is out of scale with the Towns of Kent and Patterson. Reduced scale alternatives that comply in all respects with both Towns' Codes must be presented as under SEQRA it is the lead agency's duty to act and choose among alternatives and mitigate to the maximum extent practicable adverse environmental impacts. Given the project's present design, those findings cannot be made.

 

CWCWC and PCCPOS look forward to the continued review of this project which should include a full SEIS and public scoping resulting in reduced scale alternatives and the SEIS should include full and accurate information concerning the project's full range of impacts while answering all of the issues raised by John Canning, P.E., Hydrogeologist John Conrad, David Clouser, P.E., Marian Rose, Ph.D. and this correspondence.

                                                                                               

                                                                                                Sincerely,

 

 

                                                                                                James Bacon

                                                                                                Attorney for CWCWC and

                                                                                                PCCPOS

 

 

 

 


3- This information is contained in Table 2.2 on page 9 of the Phase II Report indicating that the export coefficient for forested land is 0.5 kilograms per hectare per year. A hectare is 2.4 acres. The accurate conversion is calculated by multiplying the lbs/acre/yr by 1.12 to obtain the kilograms per hectare.


4-See DEC publication "Reducing the Impact of Stormwater Runoff from New Development" (1992) pgs. 21 and 39 - forest data from "Northern Virginia".

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
     
 
 


HOME | FILTRATION BATTLE | MEETINGS | ISSUES| NEWSLETTER | VIDEOS | MAPS | LINKS | ARCHIVES | DEVELOPMENTS
MEMBER GROUPS | BOARD OF DIRECTORS | ACTION NEEDED | CONTACT US | JOIN US